监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 签约案例 | 购买价格 | 在线试用 | 手机APP | 产品资料
X 关闭
软件项目管理工具

当前位置:工程项目OA系统 > 建筑OA系统 > 软件项目管理工具

2010年PMP美国项目管理考试习题及答案三十四

申请免费试用、咨询电话:400-8352-114

QUEST A comparison of completion status to baseline is referred to as _____. 
A Earned value measurement. 
B Percent complete. 
C ACWP. 
D BCWS 
E None of above. 
参考答案:A

QUEST The logical relationship that communicates a delay between the start/finish of one activity and the start/finish of another activity is referred to as: 
A Slack 
B Free float. 
C Restricted float. 
D Level float. 
E Lag 
参考答案:E

QUEST Overlapping activities on a project, such as design and construction, is referred to as: 
A Fast tracking 
B Risk conversion. 
C Parallel management. 
D Process improvement. 
E Synchronous manufacturing 
参考答案:A

QUEST A computer tape which contains historical project information is called ____ tape. 
A Database 
B Baseline. 
C Archive. 
D Lessons learned. 
E Life cycle summary. 
参考答案:C

QUEST Which method shown below is acceptable for reducing cost or shortening the schedule? 
A "Crashing" 
B Changing scope. 
C Performing activities in parallel rather than in series. 
D All of the above. 
E A and C only. 
参考答案:D

相关试题:

2010年PMP美国项目管理考试习题及答案三十三

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件