2010年PMP美国项目管理考试习题及答案十九
QUEST The most difficult decision for the executive sponsors to make at the end-of-phase review meeting is:
A Budget allocations for the next phase.
B Authorizing scope changes for the next phase.
C Authorizing budget increases for the next phase based upon scope changes.
D Canceling the project.
E All of the above.
参考答案:D
QUEST The financial closeout of a project dictates that:
A All project funds have been spent.
B No charge numbers have been overrun.
C No follow-on work from this client is possible.
D No further charges can be made against the project.
E All of the above.
参考答案:D
QUEST A project can best be defined as:
A Series of non-related activities designed to accomplish single and multiple objectives.
B Coordinated effort of related activities designed to accomplish a goal without a well-established end point.
C Cradle-to-grave activities which must be accomplished in less than one year and consumes human and non-human resources.
D Any undertaking with a definable time frame, well-defined objectives, and consumes both human and non-human resources with certain constraints.
E All of the above.
参考答案:D
QUEST The project scope/charter baseline includes:
A Summary of background conditions defining the project.
B Organization, authority and responsibility relationships.
C Functions to be performed.
D Resource requirement schedule including time estimates.
E All of the above.
参考答案:E

QUEST Scope reporting is the timely determination, _____, and _____ of project progress, status data, and transforming this into structured documentation (reports) necessary to judge project performance (reporting on work packages).
A Recording, accumulation.
B Recording, graphical display.
C Accumulation, graphical display.
D Graphical display, interpretation.
E Interpretation, analysis.
参考答案:A