QUEST Time management is the allocation of time in a project's life cycle through the process of:
A Planning
B Estimating.
C Scheduling.
D Controlling
E All of the above.
参考答案:E
QUEST Using the situation shown in the Special window and assuming continues efficiency for work-in-progress and fixed price contract for task four. The estimate at completion is:
A $19K
B $21K
C $26K
D $29K
E indeterminate
参考答案:C
QUEST Using the situation stated in the Special window, a comparison of the cost variance of August as compared to July shows that the magnitude ($ value) of the variance has _____ and the percentage change has _____.
A Become worse, become worse
B Become worse, improved
C Improved, increased
D Improved, become worse
E None of the above are correct
参考答案:B
QUEST The computation for Cost Performance Index is:
A BCWP/ACWP
B BCWP-ACWP
C BCWP-BCWS
D ACWP/BCWP
E ACWP-BCWS
参考答案:A

QUEST When comparing the cost of competing projects, which of the following is typically NOT considered?
A Opportunity costs.
B Direct costs.
C Sunk costs.
D Indirect costs.
E Burden rates.
参考答案:C