2010年PMP美国项目管理考试习题及答案二十七
QUEST Excessive flexibility in specifying requirements will _____ the likelihood of time overruns.
A Reduce.
B Eliminate.
C Double
D Increase
E Not affect
参考答案:D
QUEST The key purpose of project control is to:
A Plan ahead for uncertainties.
B Generate status reports.
C Keep the project on track.
D Develop the project road map.
E All of the above.
参考答案:C
QUEST Fast tracking means to:
A Speed up a project through parallel tasks.
B Swap one task for another.
C Reduce the number of tasks if possible.
D B and C.
E None of the above.
参考答案:A
QUEST As a project is carried out and slack time is consumed on individual tasks, the slack left over for the remaining tasks is:
A Insignificant.
B Reduced.
C Unchanged.
D Increased.
E Doubled.
参考答案:C

QUEST The purpose of a dummy activity in an activity-on-arrow diagram is to:
A Identify a task that could be replaced by another.
B Take the slack time into account.
C Show a task that is not necessarily needed.
D Denote a milestone.
E Show a dependency relationship.
参考答案:E