成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼
2010年PMP美国项目管理考试习题及答案二十六
QUEST In crashing a task, you would focus on:
A As many tasks as possible.
B Non critical tasks.
C Accelerating performance of tasks on critical path.
D Accelerate performance by minimizing cost.
E A and D.
参考答案:C
QUEST Using the problem stated in the Special window, Calculate the expected value of duration (in days) using the PERT concept of the expected duration of a task
A 8
B 8.8
C 9.1
D 9.7
E 10.5
参考答案:B
QUEST Using the WBS in the Special window, an instance of a work package is:
A Build house
B Excavate
C Prepare Foundation
D B and C
E None of the above
参考答案:E
QUEST All of the following are categories of a milestone in a schedule except:
A End date.
B Contract dates.
C Key events scheduled.
D Imposed dates.
E Task duration.
参考答案:E

QUEST The actual configuration of a PERT/CPM network _____ the amount of resources that can be devoted to the project.
A Increases.
B Is not affected by
C Does not require
D Is heavily dependent upon
E Is the only means of determining
参考答案:D
相关试题:
2010年PMP美国项目管理考试习题及答案二十五
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3

