成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼
2010年PMP美国项目管理考试习题及答案三十五
QUEST In general, attempts to smooth out period to period resources will _____ the scheduled time and _____ project costs.
A Increase, decrease.
B Increase, increase
C Increase, increase or decrease.
D Decrease, decrease.
E Decrease, increase.
参考答案:B
QUEST Assigning resources in an attempt to find the shortest project schedule consistent with fixed resource limits is called resource _____.
A Allocation.
B Partitioning
C Leveling
D Quantification.
E None of above.
参考答案:A
QUEST Smoothing out resource requirements from period to period is called resource _____.
A Allocation.
B Partitioning
C Leveling.
D Quantification
E None of above.
参考答案:C
QUEST Guidelines for estimating time durations include:
A Assuming a normal level of labor and equipment.
B Assuming a normal work week.
C Using consistent time units
D Using past actual durations as guides.
E All or part of each of the above.
参考答案:E
.jpg)
QUEST Which of the following networking methods allows us to show that the last 10% of one element cannot be completed until 62% of a previous element has been completed?
A PERT
B ADM
C PDM
D All of the above.
E A and C only.
参考答案:C
相关试题:
2010年PMP美国项目管理考试习题及答案三十四
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3

