监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 签约案例 | 购买价格 | 在线试用 | 手机APP | 产品资料
X 关闭
软件项目管理工具

当前位置:工程项目OA系统 > 建筑OA系统 > 软件项目管理工具

2010年PMP美国项目管理考试习题及答案二十五

申请免费试用、咨询电话:400-8352-114

QUEST A(n) _____ is defined as a specified accomplishment  in a particular instant in time which does not consume time or resources. 
A Activity 
B Event. 
C Correlation 
D Constant 
E Event constrained within planned effort. 
参考答案:B

QUEST Which of the following impacts the critical path? 
A Changing the task duration. 
B Reduce the free float of an activity. 
C Executing a backward pass 
D A or B 
E None of the above. 
参考答案:A

QUEST The range of time allowed for an activity to be completed in is the _____. 
A Planned time (Duration). 
B Float time (LS - ES, or LF - EF). 
C Critical time (when ES = LS, or EF = LF). 
D Scheduled time (LF - ES). 
E Event. 
参考答案:D

QUEST Free float is the amount of time that an activity may be delayed with out affecting the _____. 
A Early start of the succeeding activities. 
B Late start of the succeeding activities. 
C Project finish. 
D Cost of the project. 
E None of the above. 
参考答案:A

QUEST Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration. 
A 0.5 
B 1 
C 1.8 
D 2.2 
E 2.8 
参考答案:C

相关试题:

2010年PMP美国项目管理考试习题及答案二十四

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件