成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼
2010年PMP美国项目管理考试习题及答案三十六
QUEST In the PDM, common constraints include:
A Start-to-start
B Finish-to-start
C Finish-to-finish
D B and C only
E A, B, and C.
参考答案:E
QUEST Activities with zero time duration are referred to as:
A Critical path activites.
B Noncritical path activities.
C Slack time activities.
D Dummies
E None of above.
参考答案:D
QUEST In the arrow diagramming method (ADM), _____ do not consume time or resources.
A Events.
B Activities
C Slack elements.
D B and C only.
E All of the above.
参考答案:A
QUEST On a precedence diagram, the arrow between two boxes is called:
A An activity.
B A constraint.
C An event.
D The critical path.
E None of above.
参考答案:B
.jpg)
QUEST A project element which lies between two events is called:
A An activity.
B A critical path method.
C A slack milestone.
D A timing slot.
E A calendar completion point.
参考答案:A
相关试题:
2010年PMP美国项目管理考试习题及答案三十五
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3
本文内容来自自互联网公开信息或用户自发贡献,该文观点仅代表作者本人,版权归原作者所有。本站仅提供信息存储空间服务,不拥有所有权,不承担相关法律责任。若发现侵权或违规内容请联系电话4008352114或邮箱442699841@qq.com,核实后本网站将在24小时内删除侵权内容。

