2010年PMP美国项目管理考试习题及答案十六
QUEST Scope management is:
A a project control function.
B employs change control.
C a work authorization process.
D considers Cost, Quality and Schedule.
E All of the above.
参考答案:E
QUEST Which percent of the total project labor hours are typically expended by the end of the second phase of the project life cycle?
A 5%
B 10%
C 15%
D 25%
E 50%
参考答案:D
QUEST Which of the following factors has historically been the greatest contributor to project failure?
A Planning performed by a planning group.
B Poor financial estimates.
C Lack of sufficient management reserve.
D Lack of management support.
E Not using an automated tracking tool.
参考答案:D
QUEST Which of the following planning considerations is often overlooked?
A Planning for project termination.
B Qualified project manager assignment.
C Insuring top management support.
D Clearly defined tasks.
E All of the above.
参考答案:A

QUEST The project stakeholders should be actively involved with the _____ phase(s) of the life cycle.
A Conceptual
B Development.
C Execution
D Finish
E All of the above.
参考答案:E