成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼
2010年PMP美国项目管理考试习题及答案三十九
QUEST The Cost Performance Index (CPI) measures:
A cost of work performed vs planned costs.
B work performed vs cost of work performed.
C work performed vs planned work.
D direct costs vs indirect costs.
E floating costs vs. sunk costs.
参考答案:B
QUEST Parametric estimates are based on variables such as:
A Detailed planning and cost restraints.
B Physical characteristics and historical data.
C The WBS and similar projects.
D Project objectives and manpower allocations.
E Precise measurements and multiple inputs.
参考答案:B
QUEST Cost and schedule data are usually integrated because:
A optimized project cash flow can affect financial requirements
B they provide MIS with an integrated system to produce reports
C they control escalation allowances
D they account for omissions in the definitive estimate
E they predict future performance
参考答案:E
QUEST Continually measuring and monitoring the actual cost versus the budget is done to _____.
A analyze the reasons for variances
B establish the variances
C identify the problems
D All of the above.
E None of the above.
参考答案:D

QUEST Using the cumulative cost curve in the special window, height B represents
A actual cost to date
B total budgeted costs for the project
C planned cost for month 6
D cost variance
E earned value
参考答案:B
相关试题:
2010年PMP美国项目管理考试习题及答案三十八
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3

