2010年PMP美国项目管理考试习题及答案十七
QUEST Make or buy decisions are usually made during the _____ phase of a project.
A Conceptual
B Development.
C Implementation
D Execution
E Close-out
参考答案:B
QUEST Historical records during close-out are useful to _____ and _____ for future projects.
A Predict trends, highlight problems.
B Analyze successes, shortfalls.
C Analyze strengths, document results.
D Support litigation, defend claims.
E Justify results, set standards.
参考答案:A
QUEST A clear definition of the user's needs serves as the direct basis for the:
A Work breakdown structure.
B Functional requirements.
C Project cost estimate.
D Selection of personnel.
E Termination decision.
参考答案:B
QUEST Middle (functional) managers have the greatest influence in the direction of the project in which type of organizational structure?
A Project.
B Strong matrix.
C Weak matrix.
D Project coordinator.
E Project expeditor.
参考答案:C

QUEST The project charter:
A Expresses upper management commitment to the project.
B Provides that authority by which the project will be run.
C Establishes that organizational structure with the project.
D Specifies overall objectives and timeframe of the project.
E All of the above.
参考答案:E