2010年PMP美国项目管理考试习题及答案二十八

申请免费试用、咨询电话:400-8352-114

QUEST On November 1, $1000 worth of work on task A was supposed to have been done (BCWS); however, the BCWP was $850.  Calculate the schedule variance: 
A ¥-100 
B ¥100 
C ¥-150 
D ¥150 
E 85% 
参考答案:C

QUEST A plan has budgeted three weeks of effort for consultants, but the job was done in only two weeks.  Calculate the variance: 
A 1.50% 
B 33.00% 
C 75% 
D 67% 
E None of the above. 
参考答案:B

QUEST Resource leveling will often affect the project by making it: 
A Shorter. 
B Longer 
C More responsive to customer needs. 
D A and C 
E B and C. 
参考答案:B

QUEST Using the figure in the Special window,  The slacktime in Activity "G" is _____ weeks. 
A 2 
B 3 
C 4 
D 5 
E 7 
参考答案:C

QUEST Using the figure in the Special window,  Activity "D" has a latest start time of _____ weeks and a latest finish time of _____ weeks. 
A 2, 10 
B 4, 12 
C 6, 14 
D 7, 15 
E 9, 17 
参考答案:A

相关试题:

2010年PMP美国项目管理考试习题及答案二十七

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件