2010年PMP美国项目管理考试习题及答案五十三
QUEST Using the situation stated in the Special window, WBS Element Q is _____ budget by _____ percent.
A Over, 16.66
B Under, 16.66
C Over, 10.0
D Under, 10.0
E None of the above.
参考答案:A
QUEST Using the situation stated in the Special window, the schedule performance index (SPI) for WBS Element P is:
A 1.1
B 0.9
C 0.956
D 1.15
E 0.869
参考答案:A
QUEST Using the situation stated in the Special window, the cost performance index (CPI) for WBS Element R is:
A 0.875
B 1.14
C 0.952
D 0.833
E 1.2
参考答案:B
QUEST Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?
A Element P
B Element Q
C Element R
D Element S
E None of the above.
参考答案:C

QUEST Using the situation stated in the Special window, which WBS element is behind schedule but under budget?
A Element P
B Element Q
C Element R
D Element S
E None of the above.
参考答案:D