2010年PMP美国项目管理考试习题及答案十四
QUEST Documented work authorization provide:
A a means of effective internal coordination of the project's activities.
B an audit trail of all work authorized from project initiation to completion.
C a means for communication of work activity between the project manager and the performing activities.
D All of the above
E A and B only.
参考答案:D
QUEST The project life-cycle can be described as:
A project concept, project planning, project execution, and project close-out.
B project planning, work authorization, and project reporting.
C project planning, project control, project definition, WBS development, and project termination.
D project concept, project execution, and project reporting.
E All of the above.
参考答案:A
QUEST A Work Breakdown Structure:
A assures all work is identified
B subdivides the project into manageable segments
C provides the project sponsor with a time-phase task summary
D both A and B
E All of the above.
参考答案:D
QUEST Scope Management:
A entails managing the project's work content.
B is a subset of configuration management and as such is performed by CM specialists.
C is concerned with naming all activities performed, the end products which results and the resources consumed.
D is not a concern of the project manager.
E None of the above.
参考答案:C

QUEST Feasibility studies occur in which life cycle phase (s)?
A Conceptual
B Conceptual or Development
C Execution
D Preliminary planning
E any life cycle phase
参考答案:A