监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 签约案例 | 购买价格 | 在线试用 | 手机APP | 产品资料
X 关闭
软件项目管理工具

当前位置:工程项目OA系统 > 建筑OA系统 > 软件项目管理工具

2010年PMP美国项目管理考试习题及答案三十三

申请免费试用、咨询电话:400-8352-114

QUEST The starting point in the development of a top-down PERT/CPM chart is the _____ . 
A Project specification tree. 
B Customer's deliverable list. 
C Customer's milestone dates. 
D Work breakdown structure. 
E Listing of customer team meeting dates. 
参考答案:D

QUEST The critical path in a network is the path that: 
A Has the greatest degree of risk. 
B Will elongate the project if the activities on this path take longer than anticipated. 
C Must be completed before all other paths. 
D All of the above. 
E A and B only. 
参考答案:B

QUEST The major difference between PERT and CPM networks is: 
A PERT requires three time estimates whereas CPM requires one time estimate. 
B PERT is used for construction projects whereas CPM is used for R & D. 
C PERT addresses only time whereas CPM also includes cost and resource availability. 
D PERT requires computer solutions whereas CPM is a manual technique. 
E PERT is measured in days whereas CPM uses weeks or months. 
参考答案:A

QUEST A calendar that identifies when a project may be performed on an activity is called a: 
A Project calendar. 
B Resource calendar. 
C Milestone point. 
D Key point. 
E Work unit. 
参考答案:A

QUEST Planning activities such that predetermined resource availability pools are not exceeded is called: 
A Resource leveling. 
B Manpower leveling. 
C Resource limited planning. 
D Manpower planning. 
E Manpower contingency planning. 
参考答案:C

相关试题:

2010年PMP美国项目管理考试习题及答案三十二

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:55    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件