成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼
2010年PMP美国项目管理考试习题及答案四十二
QUEST Using the situation stated in the Special window, what is the cost performance index for Case #9?
A 1.1
B 1.91
C 0.83
D 1.2
E None of the above
参考答案:A
QUEST Sunk costs are:
A future costs held in reserve.
B costs invested in commodities.
C expended costs over which we have no control.
D expended costs over which we have no more control
E tax credits
参考答案:D
QUEST Managerial Reserves are:
A allowances to account for price changes that can occur over the life of a project.
B incentive fees paid to managers for good performance.
C funds used to offset poor cost or schedule estimates.
D accounts to allocate and maintain funds for contingency programs
E All of the above.
参考答案:D
QUEST Life Cycle Costing:
A is the concept of including all costs within the total life of a project.
B is an activity devoted to optimizing cost/performance
C is an activity of appraising the cost and technical performance of a completed project.
D is a process of predicting the life of a project.
E None of the above.
参考答案:A

QUEST Using the situation stated in the Special window, what is the schedule variance for Case #8?
A 1000
B 2000
C -1000
D -2000
E 0
参考答案:C
相关试题:
2010年PMP美国项目管理考试习题及答案四十一
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3

