2010年PMP美国项目管理考试习题及答案二十二
QUEST A completion of a local government study resides on your critical path. This would most likely be referred to as:
A Soft logic
B Hard logic
C An external dependency
D A mandatory dependency
E A lost cause
参考答案:C
QUEST Which of the following can affect network durations?
A Skills of the resource pool
B Calendar dates
C Constraints
D All of the above
E A and B only
参考答案:E
QUEST Sources for data on activity durations and resource requirements can be gathered from which of the following:
A Past project records (historical data)
B Commercial techniques (standard practices, rules of thumb)
C Past project team members knowledge (experience, oldtimers)
D All of the above
E A and C only
参考答案:D
QUEST The erection of foundation formwork before the placement of foundation concrete would be an example of a _____ dependency.
A Discretionary
B Mandatory
C External
D Soft logic
E Subcontracted
参考答案:B

QUEST "Hard logic" in the preparation of a network refers to:
A Discretionay dependencies
B External depenencies
C Mandatory dependencies
D All of the above
E A abd B only
参考答案:C