监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 签约案例 | 购买价格 | 在线试用 | 手机APP | 产品资料
X 关闭
软件项目管理工具

当前位置:工程项目OA系统 > 建筑OA系统 > 软件项目管理工具

2010年PMP美国项目管理考试习题及答案四十一

申请免费试用、咨询电话:400-8352-114

QUEST Cost forecasting calculations include: 
A EAC = ACWP + (BAC - BCWP) 
B EAC = BAC/CPI 
C EAC = ACWP + (BAC/CPI) 
D All of the above. 
E A and B 
参考答案:E

QUEST The Cost Performance Index (CPI) measures 
A total costs 
B performance over a period of time 
C costs at a point of time 
D variable costs 
E All of the above. 
参考答案:C

QUEST Parametric cost estimating involves 
A using the WBS to do bottom up estimates 
B defining the perimeters of the life-cycle 
C calculating the individual estimates of work packages 
D using a statistical model to estimate costs 
E A and C 
参考答案:D

QUEST Which of the statements regarding benefit-cost analysis in the Special window are true? 
A 1 and 2 
B 2 and 3 
C 1 and 3 
D 1, 2 and 3 
E None of the above. 
参考答案:C

QUEST Present value measures 
A the value to us today of future cash flows. 
B the rate of return on an investment when we take account of cash inflows and outflows 
C the current estimates of our project budget 
D the dollars worth of work accomplished as of today 
E All of the above. 
参考答案:A

相关试题:

2010年PMP美国项目管理考试习题及答案四十

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件