成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼
2010年PMP美国项目管理考试习题及答案四十
QUEST Value engineering/Analysis is the systematic use of techniques which does not include _____.
A establishing values for required functions
B provide the required functions at the lowest overall cost.
C identifies the required function of an item
D seeks to trade performance for cost
E None of the above.
参考答案:D
QUEST The ability to achieve cost savings is inversely proportional to _____.
A the earned value achieved to date
B the estimated costs to complete
C empowerment to the P.M.
D productivity
E None of the above.
参考答案:A
QUEST The estimated cost to complete (ETC) is _____.
A BCWP/ACWP
B the forecasted and final cost - cost to date
C (ACWP-BCWP)/BCWP * 100
D Total estimate - ACWP
E None of the above.
参考答案:B
QUEST Considering alternate suppliers is a form of _____.
A Value engineering.
B Risk Analysis
C Contract Management
D Project integration
E All of the above.
参考答案:A

QUEST You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid. The correct conclusion is:
A The project is operating at a favorable cost efficiency ratio.
B the project is spending more than planned
C the project is behind schedule
D the project is ahead of schedule
E B and C
参考答案:C
相关试题:
2010年PMP美国项目管理考试习题及答案三十九
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3
本文内容来自自互联网公开信息或用户自发贡献,该文观点仅代表作者本人,版权归原作者所有。本站仅提供信息存储空间服务,不拥有所有权,不承担相关法律责任。若发现侵权或违规内容请联系电话4008352114或邮箱442699841@qq.com,核实后本网站将在24小时内删除侵权内容。

