2010年PMP美国项目管理考试习题及答案五十八

申请免费试用、咨询电话:400-8352-114

QUEST The risk of accepting a lot of poor quality, in acceptance sampling, is referred to as: 
A buyer's risk 
B consumer's risk 
C producer's risk 
D type I error 
E B and D only 
参考答案:B

QUEST Standard "Shewhart" control charts assume that the distribution of sample means is: 
A uniform 
B normal 
C discrete 
D symmetrical 
E B and D only 
参考答案:E

QUEST The specification for a particular part is 10" + or - 0.015". The standard associated process produces parts with a means of 10" and standard deviation of 0.002'. The process capability index is: 
A 0.002 
B 1 
C 2.5 
D 7.5 
E None of the above 
参考答案:C

QUEST Random cause or system variation is: 
A generally present in every process 
B the responsibility of the inspection of the process 
C the responsibility of the workers of the process 
D the responsibility of management 
E A and D only 
参考答案:E

QUEST The centerline of a standard "Shewhart' control chart represents: 
A the process target 
B the nominal dimension specified by the customer 
C the nominal dimension specified by the designer 
D the true process average or mean 
E the process sample average or mean 
参考答案:E

相关试题:

2010年PMP美国项目管理考试习题及答案五十七

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件