成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼
2010年PMP美国项目管理考试习题及答案28
QUEST Which is not one of the five classifications of work found in a purchasing operafion?
A Management
B Buying
C Follow-up and expediting
D Marketing
E Clerical
参考答案:D
QUEST _____ is based on information gathered and analyzed about demand and supply. This forecast provides a prediction of short and long term prices and the underlying reasons for those trends.
A Demand forecast
B Price forecast
C Supply forecast
D Production forecast
E None of the above.
参考答案:B
QUEST Fixed-price and incentive-type contracts place responsibility for performance and financial risks associated with delay or non-performance on the:
A Buyer
B Third party
C Contractor
D All of the above
E None of the above
参考答案:C
QUEST The _____ specification delineates specific measurable capabilities or parameters for which a product can be tested as part of the acceptance procedure.
A Performance
B Functional
C Technical
D Base Line
E None of the above.
参考答案:A

QUEST There are four methods of government procurement. Which is not one of these methods?
A Assistance
B Sealed bidding
C Competitive proposals
D Acquisition
E Small purchases
参考答案:D
相关试题:
2010年PMP美国项目管理考试习题及答案27
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3

