2010年PMP美国项目管理考试习题及答案21
QUEST Giving a part of project work to a contractor is an example of:
A risk mitigation
B risk assignment
C risk delegation
D risk deflection
E risk assumption
参考答案:D
QUEST Risk management methodology should be adhered to in:
A construction projects
B system projects
C complex projects
D large projects
E All of the above.
参考答案:E
QUEST Which of the following activities can be considered as part of risk mitigation
A risk identification
B purchasing insurance
C assessment of outcomes
D assessment of probabilities
E C and D only
参考答案:B
QUEST Which of the following scheduling methods uses more of the risk management concepts:
A ADM
B PDM
C CPM
D PERT
E Gantt
参考答案:D

QUEST Which of the following utility functions reflects risk-aversion:
A uniform
B increasing
C decreasing
D exponential
E B and D only
参考答案:C
相关试题:
2010年PMP美国项目管理考试习题及答案20
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3
本文内容来自自互联网公开信息或用户自发贡献,该文观点仅代表作者本人,版权归原作者所有。本站仅提供信息存储空间服务,不拥有所有权,不承担相关法律责任。若发现侵权或违规内容请联系电话4008352114或邮箱442699841@qq.com,核实后本网站将在24小时内删除侵权内容。