QUEST Risks include the following types:
A Business risk
B pure risk
C Insurable risk
D A and B
E All of the above.
参考答案:E
QUEST The ability to reduce risk is _____ to how far you have progressed through the project life cycle.
A inversely proportional
B directly proportional
C not related
D the responsibility of the risk executive
E is directly proportional to the amount at stake.
参考答案:A
QUEST Final risk quantification considers total risk impacts and _____ .
A translates the impacts into economic terms for analysis.
B concentrates on schedule impacts
C may not consider safety and environmental impacts
D A and B
E A and C
参考答案:E
QUEST Risk management requires an understanding that _____ .
A the degree of greatest uncertainty occurs in the Conceptual Phase of the Life Cycle.
B risk identification must be directly aligned with the Work Breakdown Structure.
C it is merely advanced preparation for possible adverse future events.
D it does not imply complete control of events
E All of the above.
参考答案:E

QUEST "Fast-tracked" projects awarded and begun before all planning and risk assessment information is complete and available may _____ .
A be completed in reduced overall time than other projects.
B be in a higher risk category than other projects.
C not be compatible with project risk and assessment
D A and B
E All of the above.
参考答案:D