2010年PMP美国项目管理考试习题及答案9

申请免费试用、咨询电话:400-8352-114

QUEST The project manager must receive reports and briefings from engineers, contracting officers, procurement personnel and marketing people.  The project manager's communication dilemma is one of: 
A encoding 
B decoding 
C choice of a medium 
D one-way communication 
E All of the above. 
参考答案:E

QUEST The way a project manager sends and receives information depends upon: 
A How others relate to the project manager 
B The project manager's level in the organizational hierarchy 
C the size and nature of the project 
D the project manager's salary and age 
E the number of projects going on at one time in the company 
参考答案:A

QUEST Adding 5 people to a 4 person team increases the communication channels by a factor of: 
A 2 times 
B 3 times 
C 4 times 
D 5 times 
E 6 times 
参考答案:E

QUEST Which of the following is often overlooked in achieving effective communication? 
A speaking clearly 
B listening 
C interpreting 
D maintaining eye contact 
E manipulating the conversation 
参考答案:B

QUEST The basic elements of communication include: 
A Listening, talking and sign language. 
B Communicator, encoding, message, medium, decoding, receiver, and feedback 
C Clarity of speech and good listening habits 
D Reading, writing and listening 
E All of the above 
参考答案:B

相关试题:

2010年PMP美国项目管理考试习题及答案109

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3