2010年PMP美国项目管理考试习题及答案10
QUEST Communications is best described as:
A an exchange of information.
B providing written or oral directions.
C consists of senders and receivers
D effective listening.
E All of the above
参考答案:E
QUEST The purpose of project Risk Management is to:
A Identify those factors that will adversely impact project objectives.
B Assess the impact of adverse project factors.
C Assess the probability of adverse project factors.
D A and C
E All of the above.
参考答案:E
QUEST Project Risk Management is based on which of the following premises:
A the future is unknown.
B unknowns can result in risks or opportunities.
C we cannot control risk events.
D project risk impact can be measured and controlled
E All of the above.
参考答案:E
QUEST Risk mitigation is the process of _____ .
A transferring risk to another party.
B reducing uncertainty on the project
C identifying all possible risk events
D monitoring status and making adjustments
E All of the above.
参考答案:B

QUEST Risk exposure refers to _____ .
A the amount at stake.
B what might happen.
C the likelihood of something
D who is going to be held accountable
E All of the above.
参考答案:A