QUEST A deficiency in characteristics that render the quality of the material/service unacceptable is usually referred to as:
A defective
B defect
C non-conformance
D poor workmanship
E lack of fitness for use
参考答案:C
QUEST The formal invitation to submit a price for specified goods/services is usually referred to as:
A request for proposal
B request for quotation
C tender invitation
D bid invitation
E A and B only
参考答案:B
QUEST Which of the following is not part of contract administration
A contract award
B performance control
C financial control
D contract closeout
E All of the above are parts of contract administration.
参考答案:A
QUEST Which of the following is not part of the acquisition process:
A source selection
B invitation to bid
C contract award
D notice to proceed
E All of the above are parts of the acquisition process.
参考答案:D

QUEST Management reserve is generally intended to be used to:
A implement additional unbudgeted scope
B compensate for inaccurate estimates
C cover major unforeseen catastrophes
D cover unforeseen problems in the project
E All of the above.
参考答案:D