QUEST Which is not a consideration in a make or buy decision?
A Cost factors (least cost alternatives)
B Competitors' method of sourcing
C Existence of sufficient administration/technical personnel
D Political and social factors
E None of the above.
参考答案:B
QUEST By which means is a contractor able to control cost overruns due to changing requirements?
A Project data review
B Change order
C Purchase order amendment
D Change control
E None of the above.
参考答案:D
QUEST _____ is a formal invitation containing a scope of work which seeks a formal response (proposal) describing both methodology and compensation to form the basis of a contract.
A Request for proposal
B Invitation to bid
C Request for quotation
D Intention for bid
E None of the above.
参考答案:A
QUEST _____ is a method of procurement where a contract results from a bid which may be changed through bargaining.
A Acquisition
B Contract negotiation
C Procurement
D Purchase negotiation
E None of the above.
参考答案:B

QUEST _____ is a narrative description of the work to be accomplished or resource to be supplied.
A Purchase order
B Level of effort work
C Scope of work
D Contract stipulation
E None of the above.
参考答案:C
相关试题:
2010年PMP美国项目管理考试习题及答案28
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3
本文内容来自自互联网公开信息或用户自发贡献,该文观点仅代表作者本人,版权归原作者所有。本站仅提供信息存储空间服务,不拥有所有权,不承担相关法律责任。若发现侵权或违规内容请联系电话4008352114或邮箱442699841@qq.com,核实后本网站将在24小时内删除侵权内容。