QUEST Which of the following areas are addressed in risk identification:
A environmental
B technical
C legal
D All of the above.
E A and B only
参考答案:D
QUEST Monte Carlo simulation:
A Was originally developed by Dr. Carlo
B Is a European technique for assessing project risks
C assumes the future risk events will occur at random according to predetermined probability distributions
D is a technique to stimulate create risk event resolution
E A, B and C only
参考答案:C
QUEST Which of the following actions is an example of risk response:
A adjust project parameters (scope, time, quality ...)
B reduce the probability of potential project risk events
C reduce the consequences of potential project risk events
D wait until a problem actually happens, then deal with it in the most effective and efficient manner.
E A, B and C only
参考答案:E
QUEST Total project risk can be defined as:
A the sum of the probabilities of project risks events times the sum of consequences of those risks
B the sum of the products of each project risk event times its consequences
C the sum of the consequences of all project risk events
D the sum of the probabilities of all project risk events
E 1 - the sum of the probabilities of all project risk events.
参考答案:B

QUEST The utility of a risk seeker is:
A negatively exponential
B positively skewed
C increasing
D decreasing
E symmetrical
参考答案:C