2010年PMP美国项目管理考试习题及答案24
QUEST Which of the following is a formal invitation that requests a formal response that describes the method of work and associated compensation.
A Request for quotation (RFQ)
B Request for proposal (RFP)
C Request for bids (RFB)
D Invitation for bids (IFB)
E Letter of intent (LOI)
参考答案:B
QUEST Which of the following control types has the highest risk to the owner:
A Firm fixed price (FFP)
B Time and material (T&M)
C Cost plus fixed fee (CPFF)
D Cost plus incentive fee (CPIF)
E A and B only
参考答案:B
QUEST Which of the following contract types has the highest risk to the contractor:
A Firm fixed price (FFP)
B Time and material (T&M)
C Cost plus fixed fee (CPFF)
D Cost plus incentive fee (CPIF)
E A and B only
参考答案:A
QUEST Arbitration is a _____ approach to conflict management in resolving conflict disputes.
A lose-lose
B win-win
C win-lose
D lose-win
E closed door
参考答案:A
.jpg)
QUEST Which of the following is not a method of government procurement.
A Assistance
B sealed bidding
C competitive proposals
D acquisition
E small purchases
参考答案:D