2010年PMP美国项目管理考试习题及答案14
QUEST Pure Risk differs from Business Risks because Pure Risk's _____ .
A include chances of both profit or loss associated with the business.
B include chances of loss and no chances for profit associated with the business.
C must incur personal loss with business liability.
D must incur business liability associated with loss of pure profit.
E B and C
参考答案:B
QUEST Response Planning is the responsibility of the functional areas and considers
A mitigation.
B deflection.
C contingency planning.
D unforeseen occurrences.
E All of the above.
参考答案:E
QUEST Amount at Stake is the _____ .
A function of planned time/real time project costs.
B risk identified in successful project completions.
C (Standard Project Deviation + Expected Costs)/6
D cost of investment loss + least cost to restore status quo.
E inherent risk at conception altered by standard project deviations.
参考答案:D
QUEST The Delphi Method is _____ .
A used to derive a consensus arriving at a convergent solution
B useful in determining probability relating to future events.
C used with questionnaires based on established scenarios.
D continued as an iterative process until a solution is reached.
E All of the above.
参考答案:E

QUEST Risk Event Status is defined as _____ .
A Risk Probability x Amount At Stake.
B the severity of the consequences.
C how likely the event is to occur with risk.
D (Cost + Benefit + Business Risk) / Insurable Risk.
E B and C
参考答案:A