QUEST A program can best be described as:
A A grouping of related activities which last two years or more
B The first major subdivision of a project
C A grouping of projects, similar in nature, which support a product or product line and have no definable end point
D A product line
E Another name for a project
参考答案:C

QUEST Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:
A The project manager
B The functional manager
C The project sponsor
D The client
E All of the above
参考答案:A

QUEST The project charter is a document designed to tell _____ exactly what the project entails.
A The project manager
B The project office
C The project team
D The project sponsor
E Anyone associated with the project
参考答案:E

QUEST Work authorization forms are needed in order to:
A Authorize line organizations to charge against the project
B Establish an audit trail
C Develop a structured methodology for release of funds
D All of the above
E A and C only
参考答案:D

QUEST The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
参考答案:E

试题推荐:

2010年PMP美国项目管理考试习题及答案一

2010年PMP美国项目管理考试习题及答案二

2010年PMP美国项目管理考试习题及答案三

2010年PMP美国项目管理考试习题及答案四

2010年PMP美国项目管理考试习题及答案五

2010年PMP美国项目管理考试习题及答案六

2010年PMP美国项目管理考试习题及答案七

2010年PMP美国项目管理考试习题及答案八

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:55    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件