2010年PMP美国项目管理考试习题及答案二十九
QUEST Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.
A 11, 13
B 12, 14
C 13, 15
D 14, 16
E 15, 17
参考答案:E
QUEST Using the figure in the Special window, The Critical path is _____ weeks.
A 21
B 22
C 23
D 24
E 25
参考答案:D
QUEST Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?
A P
B Q
C R
D S
E T
参考答案:A
QUEST Using the figure in the Special window, By how many weeks can activity "F" slip without extending the end date of the project?
A 0
B 1
C 2
D 3
E 4
参考答案:D

QUEST Using the figure in the Special window, The critical path is:
A A-B-G
B C-G
C C-D
D E-F
E A-B-G and C-D
参考答案:B