2010年PMP美国项目管理考试习题及答案十一
QUEST Which of the following can result in misinterpretation of the statement of work?
A Using imprecise language (i.e. nearly, approximately)
B Mixing tasks, specifications, special instructions and approvals
C No pattern, structure or chronological order
D Wide variation in the size of tasks or details of work
E All of the above
参考答案:E
QUEST A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should:
A Change the scope baseline
B Prepare a variance report
C Call a meeting of the configuration control board
D Change the project's objectives
E Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline
参考答案:E
QUEST The document authorizing functional areas to charge against the project is the:
A Work authorization form
B Scope baseline
C Project charter
D Management plan
E Linear responsibility chart
参考答案:A
QUEST Going from Level 2 to Level 4 in the work breakdown structure will result in
A Less estimating accuracy
B Better control of the project
C Lower status reporting costs
D A greater likelihood that something will fall through the cracks
E None of the above
参考答案:E

QUEST Graphical displays of accumulated cost and labor hours, plotted as a function of time, are called:
A Variance reports
B S curves
C Trend analysis
D Earned value reporting
E Baseline control
参考答案:B