成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼
2010年PMP美国项目管理考试习题及答案二十一
QUEST The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:
A Work packages.
B Subtasks.
C Tasks.
D Code of accounts.
E Integration points.
参考答案:C
QUEST A task-oriented family tree of activities is a:
A Detailed plan.
B Linear responsibility chart.
C Work breakdown structure.
D Cost account coding system.
E Work package description.
参考答案:C
QUEST Management plans include all of the following except:
A Organization of project.
B Job descriptions.
C Policies and procedures.
D Linear responsibility charts.
E Scope baseline.
参考答案:E
QUEST A comprehensive definition of scope management would be:
A Managing a project in terms of its objective through the concept, development, implementation, and termination phases of a project.
B Approval of the scope baseline.
C Approval of the detailed project charter.
D Configuration control.
E Approved detailed planning including budgets, resource allocation, linear responsibility charts and management sponsorship.
参考答案:A

QUEST The process of choosing/documenting the best approach to achieve the project objectives is part of:
A The scope baseline.
B Scope authorization
C Scope definition
D Scope planning.
E All of the above.
参考答案:D
相关试题:
2010年PMP美国项目管理考试习题及答案二十
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3

