QUEST For every situation, several methods usually exist for effective communication to take place. Which of the following is least likely to be used for explaining to the team project planning guidelines?
A project office memo
B project office directive
C project team meeting
D formal report
E counseling sessions
参考答案:D
QUEST A project team member submits a suggestion on how to improve the corporate procurement process. This is an example of _____ communication
A upward
B downward
C horizontal
D diagonal
E None of the above.
参考答案:A
QUEST Job descriptions are examples of ______communications.
A upward
B downward
C horizontal
D diagonal
E None of the above
参考答案:E
QUEST The major reason why a project manager would use written instead of oral communication is:
A documentation
B feedback
C cost
D barrier elimination
E All of the above.
参考答案:A
![]()
QUEST Communication in both project and non-project-driven organizations should occur in directions.
A one
B two
C three
D four
E five
参考答案:E