2010年PMP美国项目管理考试习题及答案九十六
QUEST Obtaining team commitment depends on:
A clear and interesting job assignments
B consensus on project goals
C involvement in developing task objectives
D All of the above.
E B and C
参考答案:E
QUEST When a majority of team members must agree before a decision is reached _____.
A some team members may become alienated
B future group effectiveness may become damaged.
C the PM may lose credibility
D the project manager will most likely have to utilize a conflict resolution technique
E All of the above.
参考答案:E
QUEST Traits of a participative manager include:
A being accessible
B being an effective delegator
C holding social gatherings
D All of the above.
E A and C
参考答案:D
QUEST The Project Manager has the responsibility of knowing what kind of message to send because his _____ may avoid communications barriers.
A business interfaces
B output
C technical experience
D priorities
E training methods
参考答案:B

QUEST Which of the following is NOT a characteristic of message filtering?
A semantics
B media
C ethics
D organizational status
E reputation
参考答案:C