2010年PMP美国项目管理考试习题及答案33
QUEST Which of the following is equivalent to a lump sum contract:
A fixed price contract
B price fixing contract
C purchase order
D All of the above.
E B and C only
参考答案:A
QUEST Which of the following terms is used to describe the receipt issued by a carrier for items to be delivered to a third party:
A free on board
B receipt for merchandise
C packaging list
D loading list
E bill of lading
参考答案:E
QUEST Which of the following is associated with a buyer's request for material to meet a particular need:
A material warranty
B material guarantees
C implied warranty of salability
D implied warranty of fitness for a particular purpose
E A and C only
参考答案:D
QUEST The comprehensive review of a contractor's technical performance, cost performance, and delivery schedule, is referred to as:
A post project evaluation
B post contract evaluation
C post mortem
D procurement performance evaluation
E contractor's performance evaluation
参考答案:E

QUEST Which of the following terms refers to the situation where the work is being used for the purpose intended and so certified:
A beneficial completion
B substantial completion
C project completion
D contract closeout
E final completion
参考答案:B