2010年PMP美国项目管理考试习题及答案12
QUEST Project Risk _____ .
A should not be calculated for small projects.
B is the probability of each risk event minus the sum of the consequences of potential risk events.
C is the cumulative effect of uncertain occurrences which will adversely affect project objectives.
D cannot be quantified for first time projects.
E B or D
参考答案:C
QUEST Risk mitigation includes all but which of the following:
A Developing system (policies, procedures, responsibilities)
B Obtaining insurance against loss
C performing contingent planning
D developing planning alternatives
E identification of project risks.
参考答案:E
QUEST Deflection involves the transfer of risk by:
A Contracting out to another party
B Developing schedule alternative.
C Establishing functions under the project manager to handle risk events.
D Disaster planning and responses.
E None of the above.
参考答案:A
QUEST The formalization of management's attitude toward risk is called _____ .
A Decision Theory.
B Utility Theory.
C Decision Tree Analysis.
D Sensitivity Analysis.
E Probability Analysis.
参考答案:B

QUEST Risks that cannot be identified or evaluated _____ .
A should be deflected to the contracting officer.
B should be handled via contingency allowances.
C should be ignored, since they cannot be identified.
D should be ignored, since they are not covered in the Risk Assessment.
E C and D
参考答案:B