QUEST Configuration (baseline) control monitors performance against the
A scope baseline
B original schedule
C original budget
D All of the above.
E None of the above.
参考答案:A
QUEST A summary WBS is usually developed in the
A Conceptual phase
B implementation phase
C planning phase
D close-out phase
E All of the above phases
参考答案:A
QUEST A project may be defined as _____
A an integrated approach to managing projects
B a coordinated undertaking of interrelated activities.
C a group of activities directed by a project manger over a life cycle
D an undertaking with a defined starting point and defined objectives
E All of the above.
参考答案:D
QUEST Approval to proceed is normally made at the end of the _____ phase of a typical project.
A conceptual
B development
C implementation
D execution
E close-out
参考答案:A
.jpg)
QUEST Lessons learned are most often based upon project historical records. Lessons learned can be used to:
A See what mistakes others have made
B See how others have solved problems
C Predict trends, highlight problems and identify alternatives
D All of the above
E A and B only
参考答案:D
试题推荐:
2010年PMP美国项目管理考试习题及答案一
2010年PMP美国项目管理考试习题及答案二
2010年PMP美国项目管理考试习题及答案三
2010年PMP美国项目管理考试习题及答案四
2010年PMP美国项目管理考试习题及答案五
2010年PMP美国项目管理考试习题及答案六
2010年PMP美国项目管理考试习题及答案七
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3