成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼
2010年PMP美国项目管理考试习题及答案2
QUEST "Paraphrasing" is most closely associated with which part of the communication process?
A encoding
B decoding
C barriers
D feedback
E None of the above.
参考答案:D
QUEST If a project manager communicates a verbal message to a subordinate, and the subordinate leaves without saying a word, the project manager should assume:
A the message was understood
B the message was not understood
C the subordinate discarded the information
D the information was not appropriate
E None of the above.
参考答案:E
QUEST Communication always makes use of.
A symbols
B words
C language
D gestures
E All of the above.
参考答案:E
QUEST The swiftest and most effective communications take place among people with
A common points of view
B dissimilar interests
C advanced degrees
D the ability to reduce perception barriers
E good encoding skills
参考答案:A
.jpg)
QUEST Techniques that can improve communication include:
A establishing a single, one-way communications channel
B avoiding face-to-face communication
C using redundancy (i.e. saying it two different ways) whenever possible
D disregarding the sensitivity of your receiver
E All of the above.
参考答案:C
相关试题:
2010年PMP美国项目管理考试习题及答案一百零一
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3
本文内容来自自互联网公开信息或用户自发贡献,该文观点仅代表作者本人,版权归原作者所有。本站仅提供信息存储空间服务,不拥有所有权,不承担相关法律责任。若发现侵权或违规内容请联系电话4008352114或邮箱442699841@qq.com,核实后本网站将在24小时内删除侵权内容。

