QUEST The following individuals are responsible for determining the content of the Communications Management Plan. 
A Project Sponsor 
B Task Manager(s) 
C Director of Communications 
D Project Manager 
E参考答案:
参考答案:D

QUEST The Communications  Management Plan should contain the following: 
A Communications policy 
B Communications media 
C Reporting channels 
D Selection of appropriate media to meet specific needs 
E All of the above 
参考答案:E

QUEST An effective Project Manager does not share project _____  with the team members. 
A Vision 
B responsibility 
C solution to problems 
D accountability 
E status 
参考答案:D

QUEST Using "I" or "My' instead of "most people" or "our group" ______  message credibility. 
A decreases 
B increases 
C has no effect on 
D distorts 
E A and B 
参考答案:B

QUEST The role of the _____   can be invaluable in problem solving. 
A recognition seeker 
B devils advocate 
C dominator 
D topic jumper 
E A or C 
参考答案:B

相关试题:

2010年PMP美国项目管理考试习题及答案九十三

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:53    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件