监理公司管理系统 | 工程企业管理系统 | OA系统 | ERP系统 | 造价咨询管理系统 | 工程设计管理系统 | 签约案例 | 购买价格 | 在线试用 | 手机APP | 产品资料
X 关闭
软件项目管理工具

当前位置:工程项目OA系统 > 建筑OA系统 > 软件项目管理工具

2010年PMP美国项目管理考试习题及答案九十五

申请免费试用、咨询电话:400-8352-114

QUEST One of the most common pitfalls in effective communication is: 
A not selecting the correct medium 
B nor considering the position of the receiver 
C assuming that because a message is sent, it has been received 
D All of the above. 
E A and B 
参考答案:C

QUEST The most effective team motivator is: 
A the visibility of the team's contribution 
B the satisfaction of meeting a challenge 
C understanding the importance of the project 
D the individual's professional challenge 
E All of the above. 
参考答案:A

QUEST Clearly defined group goals are important because they _____. 
A motivate team behavior 
B cause inner tension within team members until they are met 
C encourage member interaction 
D All of the above. 
E A and C 
参考答案:D

QUEST A team may not be fully functional until each member 
A seeks consensus in decision making 
B feels personal acceptance 
C depends on the team leader for direction 
D A and B. 
E All of the above. 
参考答案:D

QUEST When all members must unanimously agree before a decision is reached 
A all members become committed 
B decisions are reached slowly 
C integrity is developed 
D future decision making ability is enhanced 
E All of the above. 
参考答案:E

相关试题:

2010年PMP美国项目管理考试习题及答案九十四

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:53    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件