成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼
2010年PMP美国项目管理考试习题及答案九十二
QUEST The following reports are normally developed during the project closure phase?
A Communications Management Plan and Lessons Learned
B Records Archive, Closure Report, lessons learned & Formal Acceptance Report
C Records Archive, Closure Report, & Specifications Document
D Communications Management Plan and Closure report
E None of the above
参考答案:B
QUEST A negative cost variance and positive schedule variance means:
A The project is under budget and ahead of schedule
B The project is over budget and behind schedule
C The project is over budget and ahead of schedule
D The project will be overrun but ahead of schedule at completion
E参考答案:
参考答案:C
QUEST A Project Status Report would include all of the following except:
A Cost and schedule reports
B Changes to scope. cost or schedule
C Narrative explanation of variances
D Personnel problems on the project
E Upcoming activities
参考答案:D
QUEST The primary source document for establishing the content of the Project Status Report is:
A The project charter
B The Project Plan
C The ASTM Project Document Guide
D The summary work breakdown structure
E参考答案:
参考答案:B

QUEST The most common form of project communication is:
A Upward to executive sponsor
B Downward to subordinates
C Lateral to the team and line organizations
D Lateral to customers
E Diagonally to the client's senior management
参考答案:C
相关试题:
2010年PMP美国项目管理考试习题及答案九十一
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3

