QUEST Project management provides organizations with a methodology to:
A Become more efficient and effective in accomplishing goals that cannot be handled well by
the traditional structure
B Manage high risk repetitive work
C Provide clients with multiple points of contact
D Provide guidance in accomplishing repetitive activities
E All of the above
A
QUEST Configuration (baseline) control monitors performance against the
A scope baseline
B original schedule
C original budget
D All of the above.
E None of the above.
A
QUEST A summary WBS is usually developed in the
A Conceptual phase
B implementation phase
C planning phase
D close-out phase
E All of the above phases
A
QUEST A project may be defined as _____
A an integrated approach to managing projects
B a coordinated undertaking of interrelated activities.
C a group of activities directed by a project manger over a life cycle
D an undertaking with a defined starting point and defined objectives
E All of the above.
D
QUEST Approval to proceed is normally made at the end of the _____ phase of a typical project.
A conceptual
B development
C implementation
D execution
E close-out
A
QUEST Lessons learned are most often based upon project historical records. Lessons learned can
be used to:
A See what mistakes others have made
B See how others have solved problems
C Predict trends, highlight problems and identify alternatives
D All of the above
E A and B only
D
QUEST A program can best be described as:
A A grouping of related activities which last two years or more
B The first major subdivision of a project
C A grouping of projects, similar in nature, which support a product or product line and
have no definable end point
D A product line
E Another name for a project
C
QUEST Ensuring that all work is both authorized and funded by contractual documentation is the
responsibility of:
A The project manager
B The functional manager
C The project sponsor
D The client
E All of the above
A
QUEST The project charter is a document designed to tell _____ exactly what the project
entails.
A The project manager
B The project office
C The project team
D The project sponsor
E Anyone associated with the project
E
QUEST Work authorization forms are needed in order to:
A Authorize line organizations to charge against the project
B Establish an audit trail
C Develop a structured methodology for release of funds
D All of the above
E A and C only
D
QUEST The scope baseline/project charter is prepared by the:
A Project manager
B Project manager and project office
C Project manager, project office and functional team
D Project manager, project office, functional team and project sponsor
E Project manager, project sponsor and customer/user
E
QUEST Typical characteristics of a work package include:
A Representation of units of work at a level where work is performed
B Clearly distinguishes one work package from all others assigned to a single functional
group
C Limits the work to be performed to relatively short periods of time
D All of the above
E A and B only
E
QUEST Problems can occur in properly defining a project because:
A Project goals may not be agreeable to all parties
B The plan was "too loose," thus allowing priorities to change
C Low turnover of project personnel
D Too much communication between the client and project personnel
E The project objectives were quantified
A
QUEST In preparing a good project definition, experienced project managers will:
A Concentrate mainly on the end product rather than costs or benefits. These come later.
B Realize that only the "tip of the iceberg" may be showing. As a project manager, you must
get beneath it.
C Understand that a project definition/plan is a dynamic rather than static tool, and thus
subject to change.
D Try to convert objectives into quantifiable terms.
E All of the above
E
QUEST Project life cycles provide a better means of measurement of progress and control. The
four phases of a project are conceptual development, _____, _____, and _____.
A Preliminary planning, detail planning, closeout
B Implementation, reporting, termination
C Development, implementation, termination
D Execution, reporting, finishing
E Implementation, termination, post-audit review
C
QUEST The contractual statement of work (CSOW)
A Must be the same as the proposal statement of work
B Does not identify reporting requirements
C Can be at a different level of detail (i.e. WBS level) than the proposal statement of work
D Identifies the contractor’s organizational structure for the project
E All of the above
C
QUEST Which of the following can result in misinterpretation of the statement of work?
A Using imprecise language (i.e. nearly, approximately)
B Mixing tasks, specifications, special instructions and approvals
C No pattern, structure or chronological order
D Wide variation in the size of tasks or details of work
E All of the above
E
QUEST A project manager believes that modifying the scope of the project may provide added value
for the customer. The project manager should:
A Change the scope baseline
B Prepare a variance report
C Call a meeting of the configuration control board
D Change the project’s objectives
E Postpone the modification until a separate enhancement project is funded after this
project is completed according to the original baseline
E
QUEST The document authorizing functional areas to charge against the project is the:
A Work authorization form
B Scope baseline
C Project charter
D Management plan
E Linear responsibility chart
A
相关推荐:
2012年pmp考试模拟试题及答案(一)
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1XX省财政厅综合办公楼给排水设计 3P
- 2MPM项目管理硕士报考条件
- 32015一级建造师《通信广电》讲义汇总(9)
- 42015年安全工程师考试《管理知识》:安全评价的内容
- 5[潍坊市]06年造价师考试6.15-30日报名
- 62015年二级建造师《水利》:防止地表水污染的具体规定
- 72015年咨询工程师《工程项目组织与管理》每日一练(5.10)
- 82015年招标师《项目管理与招标采购》名师讲义(7)
- 92015咨询工程师《咨询概论》模拟题下载(6)
- 102015年安全工程师安全生产法:特种设备安全监察部门
- 112015年咨询工程师每日一练免费在线测试(2015.3.19)
- 12安全救援道路示意平面图
- 13太阳能热水工程设计方案 7p
- 14造价工程师案例分析复习要点:有关流动资金
- 15园林水景施工组织设计
- 16某市体育中心二期工程给排水及消防施工方案86P
- 17成都加强农民集中居住区建设管理
- 182015年安全工程师考试《生产管理》练习集锦汇总(1-19)
- 192015年二级建造师《市政》:目标成本分析的目的和方式
- 202015年咨询工程师《工程项目组织与管理》每日一练(9.12)
- 21某体育场给排水施工图设计概况
- 222013年二级建造师《法规及相关知识》每日一练(3.16)
- 23上海某高层(43层)住宅工程防渗漏专项治理方案
- 24某住宅楼室外消防及弱电工程施工方案 44p
- 252015年招标师:工程建设项目规模及质量控制
- 26为什么倾斜度及岩石完整性加大嵌岩深度?
- 27工程咨询概论知识点:注册咨询工程师业务素质
- 28沉井基础的使用范围
- 29中建八局引领绿色建筑工业转型 推进装配式建筑
- 30龙丽温高速最高桥墩60层楼高 争取明年开工
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼