项目管理师考前模拟试题(二)及参考答案
1. Activity duration estimate inputs include all of the following except:
A. Resource requirements.
B. Basis of estimates.
C. Activity lists.
D. Constraints.
2. All of the following are contract types except:
A. Unit-price.
B. Make-or-buy.
C. Cost reimbursable.
D. Lump sum.
3. Initiation inputs for a project include all of the following except:
A. Product description.
B. Strategic plan.
C. Project charter.
D. Selection criteria.
4. Responses to risk threats include all of the following except:
A. Avoidance.
B. Acceptance.
C. Mitigation.
D. Rejection.
5. The process of performance reporting includes all of the following except _____________.
A. Status reporting.
B. Progress reporting.
C. Forecasting.
D. Product analysis
6. Constrained optimization methods of project selection include:
A. Scoring models.
B. Benefit-cost ratios.
C. Multi-objective programming algorithms.
D. Subjective analyses.
7. Which of the following statements concerning contract type is correct?
A. A fixed price contract contains the most risk for the buyer.
B. Cost reimbursable contracts offer sellers the highest profit potential.
C. Lump sum contracts offer sellers the greatest profit potential.
D. Unit price contracts are illegal in many jurisdictions.
8. A Work Breakdown Structure (WBS) numbering system should allow project staff to:
A. Identify the level at which individual WBS elements are found.
B. Identify configuration management milestones.
C. Estimate the costs of WBS elements.
D. Provide project justification.
9. All of the following are true quality statements except:
A. Quality improvement depends upon better definition and increased awareness of the
requirements/specifications.
B. Project quality management must address both management of the project and the product of the project.
C. Recognition of key actions required of each team member is necessary to meet quality objectives.
D. Computer-aided design systems can improve quality, but only at the expense of an increase in the cost of design.
10. All of the following are examples of tools often used in cost estimating except:
A. Parametric modeling.
B. Analogous estimating.
C. Bottom-up estimating.
D. Activity duration estimates.
11. At XYZ Inc., the hourly wage for semi-skilled workers is $14.00. The annual audit shows that fringe benefits cost 30% of basic wages, and that overhead costs are 60% of wages plus fringe benefits. What is the loaded” hourly wage for a semi-skilled worker at XYZ Inc.?
A. $27.14.
B. $28.96.
C. $30.03.
D. $29.12.
12. Of the following estimates, which most accurately reflect the actual cost of the project?
A. Conceptual estimates.
B. Order of magnitude estimates.
C. Preliminary estimates.
D. Bottom-up estimates.
13. The most crucial time for project risk assessment is:
A. When a problem surfaces.
B. During the planning phase.
C. During the close-out phase.
D. After the project schedule has been published.
14. When there is uncertainty associated with one or more aspects of the project, one of the first steps to take is to:
A. Revise project plan.
B. Conduct a risk-benefit analysis.
C. Conduct a needs analysis.
D. Increase the estimated cost of the project.
15. Including a contingency reserve in the project budget is intended to:
A. Reduce the probability of scope changes.
B. Increase the probability of scope changes.
C. Reduce the probability of a cost overrun.
D. Increase the probability of a cost overrun.
16. Given the information in the following table, what is the expected value from this risk event? Probability Result
A. -10,000.
B. - 7,500.
C. + 2,500.
D. -7,000.
17. A contractor is working on a fixed price contract that calls for a single, lump sum payment upon satisfactory completion of the contract. About halfway through the contract, the contractor project manager informs their contract administrator that financial problems are making it difficult for them to pay their employees and subcontractors. The contractor asks for a partial payment for work accomplished. Which of the following actions by the buyer is most likely to cause problems for the project? A. Starting partial payments for work accomplished.
B. Making no payments because it would violate the conditions of the contract.
C. Paying for work accomplished to date.
D. Negotiating a change to the payment conditions in the contract.
18. A precise description of a physical item, procedure, or service for implementation of an item or service is called :
A. Work package.
B. Baseline.
C. Product description.
D. Work breakdown structure (WBS) element.
19. A project should be terminated for all of the following reasons except:
A. Lack of team synergy.
B. The project no longer meets the company’s objectives.
C. The resources are not available to complete project activities.
D. Project funding has been significantly reduced.
20. One common way to compute estimated at completion (EAC) is to take the project budgeted-at-completion and:
A. Divide it by the schedule performance index.
B. Multiply it by the schedule performance index.
C. Multiply it by the cost performance.
D. Divide it by the cost performance index.
参考答案:
1.B 2.B 3.C 4.D 5.D 6.C 7.C 8.A 9.D 10.D 11.D 12.D 13.B 14.B 15.C 16.D 17.B 18.C 19.A 20.D
- 1贵州:高速公路三年建设会战 8000人奋战打通贵阳南大门
- 22013年一级建造师考试必备
- 3招标师《法律法规》2015考点:投标邀请书
- 4JGJ310-2013教育建筑电气设计规范--专家解读
- 52015年云南省招标师报名时间为5月20日-6月20日
- 62015一级建造师《工程经济》知识点:技术方案现金流量表构成要素
- 7影响装潢造价的主要因素
- 82015年咨询工程师《工程咨询概论》第四章(4)
- 92015年注册咨询工程师《工程咨询概论》考点解析(7)
- 10一带一路:离天空最近的丝绸之路唐蕃古道
- 11二级建造师《法规》知识点:承揽合同具有的法律特征
- 12水库水利枢纽工程平硐封堵施工方案6p
- 13一级建造师市政公用工程复习要点:公路结构
- 14咨询工程师考试辅导资料:线性盈亏平衡分析条件
- 152015一级消防工程师技术实务考试练习选择题2
- 162015年二级建造师辅导资料:行政诉讼证据的种类
- 17一级建造师工程经济复习要点:银行企业的利息与利率
- 18商务部推稳出口新政 禁止类将做出“有增有减”的动态调整
- 19二级建造师复习资料:事故调查的级别管辖
- 202015建设工程项目管理:不同类型的建设工程项目进度计划系统
- 212015安全工程师《事故案例分析》考试资料:整改措施
- 22[内蒙古]城市快速路工程专项施工方案
- 23吉林2015年注册监理工程师资格考试报名条件
- 24一级建造师建筑工程复习资料——房屋建筑工程竣工验收备案的范围
- 25北京市钢结构工程整体提升法安装工艺标准
- 26[湖南]高速公路工程路基土石方施工方案
- 27浅论加强农田水利建设、构建社会主义新农村
- 28影响净化过滤器的因素
- 29路基树根桩施工指导书
- 30一级建造师复习资料:木材表面清油油漆涂饰——刷清漆
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼