1. A narrative description of products or services to be supplied under contract is called:
A. The project plan.
B. A statement of work.
C. An exception report.
D. A Pareto analysis.
2. An example of scope verification is:
A. Reviewing the performance of an installed software module.
B. Managing changes to the project schedule.
C. Decomposing the WBS to a work package level.
D. Performing a benefit/cost analysis to determine if we should proceed with the pro
3. Which of the following is not an example of a source of scope change?
A. A variation in government regulations.
B. Failure to include a required feature in the design of a telecommunication system.
C. A need to engage in bottom-up cost estimating.
D. Introducing technology that was not available when scope was originally defined.
4. The subdivision of major project deliverables, as identified in the scope statement, into smaller, more manageable components is called:
A. Parametric estimation.
B. Scope definition.
C. Feasibility analysis.
D. Benefit-cost analysis.
5. The process of establishing clear and achievable objectives, measuring their achievement, and adjusting performance in accordance with the results of the measurement is called:
A. Strategic planning.
B. Alternative objectives inventory.
C. Management by objectives.
D. Contingency planning.
6. Configuration management is:
A. Used to ensure that the description of the project product is correct and complete.
B. The creation of the work breakdown structure.
C. The set of procedures developed to assure that project design criteria are met.
D. A mechanism to track budget and schedule variances.
7. A fundamental tenet of modern quality management holds that quality is most likely to be achieved by:
A. Planning it into the project.
B. Developing careful mechanisms to inspect for quality.
C. Striving to do the best job possible.
D. Conducting quality circle activities.
8. Your most recent project status report contains the following information: BCWP = 3,000, ACWP = 3,500, and BCWS = 4,000. The schedule variance is:
A. + 1,000.
B. + 500.
C. - 500.
D. - 1,000.
9. Learning curve theory emphasizes that in producing many goods:
A. Cost decreases as production rates increase.
B. Average unit cost decreases as more units are produced.
C. Materials become cheaper when they are purchased in bulk.
D. Laborers become more productive because of technological advances.
10. Rearranging resources so that constant resource levels are maintained is called:
A. Floating.
B. Leveling.
C. Restructuring.
D. Crashing. 11. The _________ is a time-phased budget that will be used to measure and monitor cost performance in the project.
A. Work breakdown structure
B. Project schedule
C. Cost baseline
D. Cost budget
12. To transfer most of the cost risk to the contractor, the client may use a ___________ contract.
A. Cost plus award
B. Cost plus incentive fee
C. Cost plus fixed fee
D. Fixed price
13. An appropriate sequence for risk management activities is:
A. Risk identification, risk quantification, and risk response development and control.
B. Risk identification, risk assessment, and risk planning.
C. Risk identification, risk mitigation, and risk management.
D. Risk identification, risk elimination, and risk mitigation.
14. Theory X holds that:
A. Quality improvements lie in the hands of quality circles.
B. Profits are tied to meeting schedule deadlines.
C. Absenteeism is tied to poor working conditions.
D. Workers are inherently unmotivated and need strong guidance.
15. All of the following are characteristics of parametric estimating except:
A. Historical information.
B. Quantifiable.
C. Scalable.
D. Activity lists.
16. Inputs to cost budgeting include all of the following except:
A. Cost baseline
B. Cost estimate
C. Work breakdown structure
D. Project schedule
17. Inputs used during scope planning include all of the following except:
A. Constraints.
B. Project charter.
C. Budget/cost analysis. D. Product description.
18. Cost control outputs include all of the following except:
A. Estimate at completion.
B. Budget updates.
C. Revised cost estimates.
D. Cost baseline.
19. Risk identification outputs include the following except:
A. Decision trees.
B. Inputs to other processes.
C. Risk symptoms.
D. Potential risk events.
20. Puts into overall change control include all of the following except:
A. Project plan.
B. Change requests.
C. Change control system.
D. Performance reports
参考答案:
1.B 2.A 3.C 4.B 5.C 6.A 7.A 8.D 9.B.10.B 11.C 12.D 13.A 14.D 15.D 16.A 17.C 18.D 19.A 20.C
- 12015年二级建造师辅导资料《法规》:记忆词条(6)
- 2一级建造师注册增项步骤是什么?
- 3深圳某建筑公司加气混凝土砌块砌体施工工艺
- 4构件运输模板及脚手架
- 5冷却塔筒身施工作业指导书
- 6一级建造师工程经济复习要点:损失时间
- 72015年二级建造师辅导资料:民事诉讼的特点
- 8云南省2015造价工程师报名
- 9从西部大开发战略中谈对雨水集蓄利用的几点认识
- 10建筑工程管理与实务复习要点:减少表面收缩裂缝
- 112015年二级建造师辅导资料:建设工程施工管理(5)
- 122015年山东临时注册消防工程师考试考场安排
- 132010年CPMP中国项目管理师考试练习题及答案十六
- 14建设工程项目管理:程序文件的编写
- 15一级建造师复习资料:机电工程项目采购管理
- 162015年造价工程师工程计价知识点:质量保证金的管理
- 17有粘结预应力FRP筋混凝土梁抗裂计算方法
- 182011城市发展与规划大会召开共商城市低碳转型与绿色发展大计仇保兴作主题报告 何权致辞
- 19招标师《法律法规》2015考点:行政监督的职责分工
- 202009年二级建造师《建设工程法规》练习题(33)
- 21[河南]铁路工程无砟轨道夏季雨季施工方案
- 22某工程塔吊超长附墙支撑设计
- 23电厂210m变坡混凝土烟囱上部结构施工工艺
- 2409年咨询工程师《宏观经济》考点解析(二十六)
- 25混凝土的性能特点
- 26咨询工程师考试重点知识辅导资料:工程项目管理的内容
- 27造价工程师复习资料:防水混凝土设计抗渗等级
- 28某超高层建筑结构设计研究综述
- 29国企改革核心:市场化资本补充机制
- 30商务部:贯彻落实《党政机关厉行节约反对浪费条例》和《党政机关国内公务接待管理规定》
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼