2012年pmp考试模拟试题及答案(三)
A Implementation Plan
B a life cycle
C Development Plan
D a critical path
E Management Plan
B
QUEST What is the purpose of the Project Plan?
A To document the Preliminary estimates.
B To document the Definitive estimates.
C To document the Budgetary estimates.
D To document Parametric estimates.
E To document Order of Magnitude estimates.
C
QUEST Scope management is:
A a project control function.
B employs change control.
C a work authorization process.
D considers Cost, Quality and Schedule.
E All of the above.
E
QUEST Which percent of the total project labor hours are typically expended by the end of the
second phase of the project life cycle?
A 5%
B 10%
C 15%
D 25%
E 50%
D
QUEST Which of the following factors has historically been the greatest contributor to project
failure?
A Planning performed by a planning group.
B Poor financial estimates.
C Lack of sufficient management reserve.
D Lack of management support.
E Not using an automated tracking tool.
D
QUEST Which of the following planning considerations is often overlooked?
A Planning for project termination.
B Qualified project manager assignment.
C Insuring top management support.
D Clearly defined tasks.
E All of the above.
A
QUEST The project stakeholders should be actively involved with the _____ phase(s) of the life
cycle.
A Conceptual
B Development.
C Execution
D Finish
E All of the above.
E
QUEST Make or buy decisions are usually made during the _____ phase of a project.
A Conceptual
B Development.
C Implementation
D Execution
E Close-out
B
QUEST Historical records during close-out are useful to _____ and _____ for future projects.
A Predict trends, highlight problems.
B Analyze successes, shortfalls.
C Analyze strengths, document results.
D Support litigation, defend claims.
E Justify results, set standards.
A
QUEST A clear definition of the user’s needs serves as the direct basis for the:
A Work breakdown structure.
B Functional requirements.
C Project cost estimate.
D Selection of personnel.
E Termination decision.
B
QUEST Middle (functional) managers have the greatest influence in the direction of the project
in which type of organizational structure?
A Project.
B Strong matrix.
C Weak matrix.
D Project coordinator.
E Project expeditor.
C
QUEST The project charter:
A Expresses upper management commitment to the project.
B Provides that authority by which the project will be run.
C Establishes that organizational structure with the project.
D Specifies overall objectives and timeframe of the project.
E All of the above.
E
QUEST The WBS is:
A An organization oriented family tree of the project.
B A task oriented family tree of the project.
C A cost centered structure of the project.
D Only required on large complex projects where separately identifiable work packages are
difficult to construct.
E None of the above.
B
QUEST Including the customer in the process of project planning is:
A Slow and counterproductive.
B Essential in the definition and documentation of project goals.
C Necessary, but of limited value.
D Unnecessary because project goals are defined in the proposal stage.
E None of the above.
B
QUEST The scope management provides:
A A basis for future decisions about the project.
B A baseline to accomplish verification measures.
C A baseline to evaluate potential scope changes.
D All of the above.
E B and C only.
D
QUEST During project execution, a line manager informs you that he will not have sufficient
resources available next month to support your and two other projects. The best way to handle
this problem would be to:
A Ask the line manager to make the decision.
B Ask the line manager to work with senior management to prioritize the work.
C Ask your sponsor to meet with the line manager.
D Ask the line manager to set up a meeting with you and the other project managers to work
out the problem yourselves.
E Prepare a purchase order to outsource the work.
D
QUEST Proper implementation of project management will guarantee that:
A Budgets will be met.
B Schedules will be adhered to.
C Quality/performance will be met.
D The project will be a success.
E None of the above.
E
QUEST The most difficult decision for the executive sponsors to make at the end-of-phase review
meeting is:
A Budget allocations for the next phase.
B Authorizing scope changes for the next phase.
C Authorizing budget increases for the next phase based upon scope changes.
D Canceling the project.
E All of the above.
D
QUEST The financial closeout of a project dictates that:
A All project funds have been spent.
B No charge numbers have been overrun.
C No follow-on work from this client is possible.
D No further charges can be made against the project.
E All of the above.
D
QUEST A project can best be defined as:
A Series of non-related activities designed to accomplish single and multiple objectives.
B Coordinated effort of related activities designed to accomplish a goal without a well-
established end point.
C Cradle-to-grave activities which must be accomplished in less than one year and consumes
human and non-human resources.
D Any undertaking with a definable time frame, well-defined objectives, and consumes both
human and non-human resources with certain constraints.
E All of the above.
D
QUEST The project scope/charter baseline includes:
A Summary of background conditions defining the project.
B Organization, authority and responsibility relationships.
C Functions to be performed.
D Resource requirement schedule including time estimates.
E All of the above.
E
QUEST Scope reporting is the timely determination, _____, and _____ of project progress,
status data, and transforming this into structured documentation (reports) necessary to judge
project performance (reporting on work packages).
A Recording, accumulation.
B Recording, graphical display.
C Accumulation, graphical display.
D Graphical display, interpretation.
E Interpretation, analysis.
A
相关推荐:2012年pmp考试模拟试题及答案(二)
- 1建筑工程项目管理软件
- 2软件项目管理工具
- 3项目管理系统
- 4工程行业科研项目管理系统
- 5工程项目管理软件下载
- 6开源项目管理系统下载
- 7工程项目管理
- 8多项目管理
- 9项目管理
- 10哪家项目管理好
- 11企业项目管理排名
- 12项目管理系统有哪些
- 1武汉施工电梯坠落对保温施工的警示
- 22015年咨询工程师《工程咨询概论》每日一练(1.2)
- 3项目开发心得之需求分析
- 4第四系底界粘土岩性对提高开采上限的影响分析
- 5一级建造师管理与实务复习要点:水泥土搅拌法
- 6安全工程师考试《法律法规》习题班讲义精选(142)
- 72015招标师《招标投标法律法规与政策》复习策略
- 82015招标师考试《法律法规与政策》讲义精髓(16)
- 9一级建造师市政公用工程管理与实务复习要点:双快水泥
- 102015年招标师《专业实务》辅导:货物评标的详细评审要点
- 112015年二级建造师《机电》:焊接中检验
- 122015.4.21咨询工程师每日一练免费在线测试
- 13某国际展览中心园林绿化施组设计
- 142015年一级建造师《公路工程》路面工程施工(9)
- 15注册安全工程师考试《安全生产技术》习题
- 16造价工程师案例分析复习要点:BEP(S)
- 17工法、申报科技进步奖的工法
- 182015招标师备考试题资料怎么复习
- 19安全工程师生产管理复习要点:起重作业
- 20未来太阳能与建筑一体化是趋势也是难题
- 212008年安全工程师考试《安全生产法及相关法律知识》习题十八
- 22某开发区污水管网施工组织设计(牵引法)30P
- 232015年造价工程师辅导:国内外法律体系(2)
- 24[北京]博物馆工程施工现场平面布置图(6张)
- 25安全工程师安全生产法复习资料——事故调查报告内容
- 262015年注册安全工程师事故案例分析模拟试题(八)
- 27中铁十八局天津外环线项目跨北环铁路预制梁体顶推顺利完成
- 28宿迁市村整办领导深入排查重点道路沿线环境整治问题
- 292010年PMP美国项目管理考试习题及答案八十二
- 30预埋通信管施工方法
成都公司:成都市成华区建设南路160号1层9号
重庆公司:重庆市江北区红旗河沟华创商务大厦18楼