QUEST Which of the following is referred to as payback period: 
A the number of periods required to recover the initial investment 
B the rate of return on  the investment 
C the number of periods required to bring project cost back to the original budget, based on current performance 
D loan payment schedule 
E None of the above 
参考答案:A

QUEST Which of the following is referred to as sunk cost: 
A management reserve 
B contingency fund 
C cost budgeted for construction under water 
D expended funds over which there is no further control 
E forecasted budget over-runs 
参考答案:D

QUEST The future value of an annual income flow of $1000 for 2 years at 10% is: 
A ¥2,200 
B ¥2,280 
C ¥2,300 
D ¥2,310 
E None of the above 
参考答案:D

QUEST The net present value of $110 one year from now at 10% is: 
A ¥100 
B ¥120 
C ¥121 
D $100 less taxes 
E $100 less taxes and interest 
参考答案:A

QUEST Which of the following depreciation methods provides for accelerated depreciation of an asset: 
A Double declining balance. 
B Straight line. 
C Exponential depreciation 
D Double sum of the years digits 
E Double increasing balance 
参考答案:A

相关试题:

2010年PMP美国项目管理考试习题及答案四十五

试题推荐:

2010年PMP美国项目管理认定考试全真模拟试题精选1

2010年PMP美国项目管理认定考试全真模拟试题精选2

2010年PMP美国项目管理认定考试全真模拟试题精选3

发布:2007-03-02 10:54    编辑:泛普软件 · xiaona    [打印此页]    [关闭]
相关文章:

泛普软件项目管理工具其他应用

项目管理工具 禅道项目管理软件 梦龙项目管理软件 微软项目管理软件 装饰管理系统 装修预算软件 项目计划软件 项目进度管理软件 软件项目管理工具 材料管理软件 工程项目管理软件系统 项目管理系统 施工管理软件 建筑工程项目管理软件 工程管理软件