2010年PMP美国项目管理考试习题及答案五十四
QUEST It is argumentative whether project managers actually control costs. Which of the following is the most common element over which the project manager may have some degree of control?
A Direct labor dollars
B Direct labor hours.
C Overhead rates.
D Procurement costs.
E None of the above.
参考答案:B
QUEST Company expenses such as auditing costs, supervision, office supplies, building rent and maintenance are elements of the:
A Capital budgeting process.
B Overhead rates.
C Contracts and administration costing system.
D Fringe benefits packages.
E None of the above.
参考答案:B
QUEST Management reserves are normally defined as a % of the total budget. As a project progresses, the project manager wants the $ value of management reserve to _____, whereas the customer wants the management reserve to _____.
A Increase, increase.
B Increase, decrease.
C Decrease, decrease.
D Decrease, increase.
E Remain the same, return to customer.
参考答案:E
QUEST The most effective means of determining the cost of a project is to price out the _____.
A Work breakdown structure.
B Linear responsibility chart.
C Project charter.
D Scope statement.
E Management plan.
参考答案:A

QUEST The most expensive phase of life cycle costing is:
A R & D.
B Applied research.
C Production
D Operations and support.
E Termination.
参考答案:D