2010年PMP美国项目管理考试习题及答案五十九
QUEST 100 % inspection of output is:
A the best proven method to ensure quality
B is expensive, ineffective approach to quality management
C can never be, justified
D can still leave some defects undetected
E B and D only
参考答案:E
QUEST Quality control charts show a characteristic of the product or service against:
A the specification limits
B customer requirements
C control limits based on three standard deviations in each direction
D control limits based on six standard deviations in each direction
E A and D only
参考答案:C
QUEST Variables quality data are:
A quantitative or qualitative data
B quality data for which the product or service is designed and built
C reflect measurements on a continuous scale of a characteristic of the produce or service.
D Indicate management's understanding of the concept of variability
E B and C only
参考答案:E
QUEST Attributes quality data are:
A quantitative or qualitative data
B quality data for which the products or services is designed and built.
C reflect measurements on a continuous scale of a characteristic of the product or service
D indicate management's understanding of the concept of variability
E A and B only
参考答案:E

QUEST Which of the following are among Phil Crosby's "absolutes of quality'.
A the performance of standard is zero defects
B do everything right the first time, each time
C constantly improve each product and each service
D the measurement system is the cost of nonconformance
E A and D only
参考答案:E
相关试题:
2010年PMP美国项目管理考试习题及答案五十八
试题推荐:
2010年PMP美国项目管理认定考试全真模拟试题精选1
2010年PMP美国项目管理认定考试全真模拟试题精选2
2010年PMP美国项目管理认定考试全真模拟试题精选3
本文内容来自自互联网公开信息或用户自发贡献,该文观点仅代表作者本人,版权归原作者所有。本站仅提供信息存储空间服务,不拥有所有权,不承担相关法律责任。若发现侵权或违规内容请联系电话4008352114或邮箱442699841@qq.com,核实后本网站将在24小时内删除侵权内容。